Project duration: January 1989 – August 1989.

Based on the requests received by DOI, detailed feasibility survey, design and cost of the scheme were prepared. The eagerness of the beneficiaries for cash and kind contribution for the implementation of the project was positive.

The feasibility study was prepared to provide information on command area, agricultural plan, irrigation source to meet crop water needs, engineering design with possible alternatives, economic developments, cost sharing and implementation arrangement between the DOI and beneficiaries etc.

The project found to be feasible for implementation which aims to irrigate 130 ha (net) of land and benefit 1586 nos. of farmers of the area.